Promises still open
Landscape screening required within 30 days of the 2016 approval is still unbuilt. The applicant now calls it “behind schedule,” with completion pushed to fall 2027 / spring 2028, and the tied “iconic fence” to 2028–29.

Summit County • CUP PLN26-004
Permit countdown
Until the permit ends Oct 13, 2033
On October 13, 2026, the Summit County Commissioners approved a 7-year extension to Quikrete’s gravel mine, asphalt and concrete plant on Highway 9 - next to a community that didn’t exist when the last permit was issued. After our appeal, the term is 7 years, not ten.
Many safety and health conditions are left unaddressed.
151
acres of gravel mine and concrete/asphalt plant
350+
concerned Silverthorne residents in the Lower Blue Valley
450
daily loaded truck trips that go by an elementary school with no monitoring
7 years
the term Quikrete received from the county
Landscape screening required within 30 days of the 2016 approval is still unbuilt. The applicant now calls it “behind schedule,” with completion pushed to fall 2027 / spring 2028, and the tied “iconic fence” to 2028–29.
The county permit caps 450 loaded truck trips a day. The separate state highway-access permit anticipates 670 daily vehicle trips, including 520 trucks over 30 feet — with no proposed change.
The application cites an 80/75 dB(A) industrial standard. Colorado's residential standard is 55/50. No document says which applies at the property line, or where it would be measured.
Our mission
Friends of Maryland Creek is a non-profit advocacy organization dedicated to protecting the families, wildlife, and natural resources of the Lower Blue River Valley. We stand united to defend our neighborhood from industrial overdevelopment, actively opposing the Quikrete gravel mine and asphalt permit extensions. Through legal advocacy, public mobilization, and rigorous environmental oversight, we demand responsible land use, clean air, and the absolute protection of the Maryland Creek watershed from corporate pollution.